The next LNG cycle will be decided by availability of transformers, not a gas price

One manufacturer is holding 122 gigawatts of gas power backlog and slot reservations. Project finance still treats the electrical scope as a procurement detail, and that is where the schedule risk now sits.

Unmute for sound.

North America intends to more than double its liquefied natural gas export capacity by 2029. The gas is there, the buyers are there, and the final investment decisions are being taken. The electrical equipment is not there. A large gas turbine ordered today arrives in about five years, around 2031. For any project that has not already reserved that equipment, the delivery slot, not the gas, now sets the date of first cargo.

The US Energy Information Administration projects export capacity rising from 11.4 billion cubic feet a day at the start of 2024 to 28.7 in 2029, most of it on the Gulf Coast. The forecast carries a condition: if projects under construction begin operations as planned. Hitachi Energy’s white paper is a careful examination of that condition.

Its central observation is that liquefaction is electrically intensive, and that LNG developers now compete for generation, grid connections, transformers, switchgear and commissioning labour with data centres and general electrification. Hitachi puts the position plainly. An industry built to export energy is bidding against the digital economy for the electricity to make it.

North American LNG export capacity
Billion cubic feet a day. Actual at the start of 2024, against the EIA forecast for 2029, which holds only if projects under construction begin operations as planned.
Start of 2024Actual
11.4 Bcf/d
2029EIA forecast
28.7 Bcf/d
Source: US Energy Information Administration, 16 October 2025.

The independent evidence sharpens the diagnosis. US electricity demand rose about five percent between 2019 and 2024, reversing a decade of flat consumption, and the EIA forecast in January 2026 the strongest four-year demand growth since 2000. Wood Mackenzie supply chain data puts lead times for power transformers and generator step-up units at two to three years. Gas turbines are worse: the Electric Power Research Institute puts a large unit ordered today at around five years, S&P Global has reported waits of up to seven, and Wood Mackenzie expects turbine prices near 600 dollars per kilowatt by end-2027, a 195 percent increase on 2019. The Department of Energy has separately found 55 percent of in-service distribution transformers, some 40 million units, are over 33 years old, so the replacement queue competes with the growth queue.

The clearest evidence sits in a manufacturer’s order book. GE Vernova reported on 28 October a combined gas power backlog and slot reservation position of 122 gigawatts, being 64 gigawatts of equipment backlog and 58 gigawatts of slot reservations, with at least 130 expected by year end. Power orders rose 178 percent organically. In those three months it contracted 11 gigawatts of new gas equipment and shipped five. The queue is lengthening, not clearing.

None of this is a reason to be bearish on LNG. The resource, market access and industrial base are real. It is a reason to be precise about what determines whether a project hits its dates.

Hitachi’s recommendation is integrated delivery, with an equipment manufacturer or integrator owning the design basis and key interfaces. The company sells exactly that, which readers can weigh, but the point stands and the paper states it well: the critical delivery question is not who supplies each component, it is who owns the performance of the complete subsystem.

What I would add sits one level up, in the financing. Large LNG projects divide electrical scope into packages so work proceeds in parallel. Every boundary creates an interface, and an interface with no owner surfaces at commissioning, the most expensive possible moment to find one. A disputed test responsibility does not appear in a cost report. It appears as a delay to energisation, with cranes, crews and milestone payments already committed.

Project finance has not caught up. Final investment decision is taken on feed gas, offtake, liquefaction technology and marine access. The electrical scope is treated as a downstream utility package, procured after the commercial concept is fixed. Yet slippage at energisation flows into capitalised interest, delayed first cargo and debt service cover in the early operating years, where the structure is tightest.

The industry has already invented the right instrument. A slot reservation agreement is a dated, priced claim on manufacturing capacity. Lenders should diligence those the way they diligence a gas supply agreement, because that is what they now are.

Three further changes follow. Put long-lead electrical equipment reservations on the critical path in the base case model rather than in the procurement annexe. Require the independent engineer to sign off the energisation date against an actual delivery slot, with evidence. And price interconnection and curtailment risk explicitly, because a grid connection on a map is not a grid connection.

Behind-the-meter generation is not the escape route it is presented as. As Hitachi concedes, it changes the boundary of the problem rather than removing it. The project still needs fuel, permits, generating equipment, transformers, protection and control, and the same scarce electricians. Reuters reported rising Gulf Coast labour costs well before the current squeeze.

Whether North America reaches the capacity the EIA projects is now a question of equipment lead times and interface ownership. Capacity that cannot be energised on schedule is not capacity. It is capitalised interest with a flare stack attached.

Key sources and references

  1. Hitachi Energy, “The power paradox: Why power infrastructure readiness will define the next wave of LNG development in North America”, September 2026.
  2. GE Vernova Inc., third quarter 2026 results, reported 28 October 2026, gas power backlog and slot reservation agreements.
  3. US Energy Information Administration, “North America’s LNG export capacity could more than double by 2029”, 16 October 2025.
  4. US Energy Information Administration, “EIA forecasts strongest four-year growth in U.S. electricity demand since 2000, fueled by data centers”, 13 January 2026.
  5. US Energy Information Administration, Electric Power Annual, Table 2.2, sales and direct use of electricity to ultimate customers, 2015 through 2025: total end use of 3,981 terawatt-hours in 2019 and 4,181 terawatt-hours in 2024.
  6. Wood Mackenzie supply chain data on transformer and generator step-up unit lead times, as summarised in POWER Magazine, “Making the connection”, September 2025.
  7. US Department of Energy, study of in-service distribution transformer age, cited in POWER Magazine (2025).
  8. Wood Mackenzie gas turbine price forecast, reported in Utility Dive, April 2026.
  9. Bobby Noble, Electric Power Research Institute, turbine delivery lead times, reported in Utility Dive, April 2026.
  10. S&P Global, “US gas-fired turbine wait times as much as seven years; costs up sharply”, 20 May 2025.
  11. Williams, C., “Rising US labor costs threaten to derail new LNG projects”, Reuters, 24 June 2024.
  12. Paul Gardner Brook, The Luxury of Delusion: AI, energy dogma and the betrayal of reality, Medium.

About the author

Paul Gardner Brook has spent more than thirty years in global financial markets, including as a Managing Director at Nomura and a Senior Vice President in Lehman Brothers’ Asia Special Situations Group. He writes on capital markets, energy and technology at paulgardnerbrook.com.

This article is general commentary on energy markets and project finance. It is not investment, legal, taxation or accounting advice, not a recommendation, and not an offer or solicitation in respect of any security or financial instrument. Figures were current at 12 November 2026 and are sourced to the organisations named in the text. Third-party figures are reported as their sources state them.